DOE's $237M SCALED Program Pays to Refurbish Transformers and Requalify Grid Inputs. The Concept Paper Is Due November 20, and It Isn't Optional.

October 30, 2026 · 10 min read

Granted Research Team · Editorial policy

On Friday, October 30, 2026, the Department of Energy's Office of Electricity (OE) published Grid Supply Chain Alternatives to Lead Energy Dominance (SCALED), Funding Opportunity DE-FOA-0003641. It offers about $237 million in cooperative agreements for one of the grid's tightest bottlenecks: transformers, switchgear, breakers, bushings, and the materials that go into them.

The deadline that matters is the earliest one. Full applications are due February 8, 2027, but only organizations that file a concept paper by 5:00 p.m. ET on Friday, November 20, 2026 may submit one. That leaves three weeks from release, including Thanksgiving week, to assemble a team, secure 50% cost share in principle, and write seven pages that DOE will use to encourage or discourage you.

This analysis covers what SCALED funds, why DOE structured it as a manufacturing program and not a research program, who is eligible, and how to use the three weeks before the concept paper deadline.

The opportunity in one table

ItemDetail
AgencyDOE Office of Electricity, administered by NETL
Opportunity numberDE-FOA-0003641 (Assistance Listing 81.122)
InstrumentCooperative agreements, "Non-Research Demonstration"
Total fundingAbout $237 million (FY2027)
Topic Area 1Refurbishment and Reuse: $50M, 3–20 awards, $2.5M–$15M each, up to 24 months
Topic Area 2Alternative Materials and Subcomponents: $187M, 7–50 awards, $1M–$25M each, up to 48 months (12-month Phase 1 plus 36-month Phase 2)
Cost shareAt least 50% of total project cost, both topics
Concept paperRequired. Due November 20, 2026, 5:00 p.m. ET. Seven pages maximum
Full applicationFebruary 8, 2027, 5:00 p.m. ET via DOE eXCHANGE
Selection noticeAnticipated June 25, 2027
Award dateAnticipated September 23, 2027
QuestionsDE-FOA-0003641@netl.doe.gov

The funding comes from the FY2026 Energy and Water appropriations act (Pub. L. 119-74, Div. B, §311(b)). Unlike much of what DOE posted in 2026, this program is backed by money Congress has already appropriated, not a pending request.

Why DOE is funding this now

The NOFO's background section summarizes the shortage. Demand for power transformers has risen 116% since 2019 and demand for distribution transformers 41%. Across other major categories of electrical equipment, demand is up 35% to 274%. DOE puts lead times at up to two years, about four times pre-2022 levels, and says prices have risen five- to six-fold over the same period. Imports are projected to supply 80% of U.S. power transformers and 50% of distribution transformers.

Manufacturers have committed nearly $2 billion to new transformer capacity, but the NOFO notes that OEMs name raw materials (grain-oriented electrical steel, copper, aluminum) and technical labor as the limits on expansion. A new factory doesn't help if the steel it needs is imported or the bushings come from one overseas supplier.

SCALED addresses two points in that chain:

  1. Topic Area 1 recovers equipment already in the field. A refurbished distribution transformer can return to service in weeks, compared with a two-year wait for a new one.
  2. Topic Area 2 qualifies domestic substitutes for constrained inputs (electrical steel, ceramic bushings, insulation, continuously transposed conductors, copper windings, chemical precursors) so that U.S. manufacturers can actually use them on production lines.

SCALED fits into a broader federal effort on grid equipment. It follows DOE's SPARK selections, which put $1.9 billion into reconductoring and grid-enhancing technologies that will themselves need transformers and switchgear, and the August bulk power system emergency order (EO 14421), which made foreign-sourced grid equipment a security issue. SCALED is the program that puts money into the domestic supply side.

The word that defines the program: "not research"

The NOFO repeats this point often enough that it amounts to the main eligibility test. SCALED is labeled a Non-Research Demonstration. DOE lists among applications "specifically not of interest" any project that includes "early-stage R&D, laboratory experimentation, fundamental technology development, or activities more appropriate for basic/applied research programs." It sets technology readiness floors of TRL 8 for Topic Area 1 and TRL 6 for Topic Area 2.

The Topic Area 2 rules state it directly. Phase 1 "must focus on planning, manufacturing readiness, supply chain formation, domestic sourcing, and customer alignment—not laboratory research, technology maturation, or early-stage R&D." Phase 2 "must emphasize production execution... not laboratory testing." Even the metrics must avoid "laboratory-based technical performance measurements, experimental benchmarking, or R&D style validation indicators."

This affects who should lead a proposal. A university materials lab with a promising new magnetic alloy at TRL 4 is not a SCALED lead applicant, however good the science. The same lab can be a valuable team member if it supports a manufacturer's qualification testing for a TRL 6+ material. The NOFO does say the Team and Resources criterion considers "past peer-reviewed publications." The successful lead applicants, though, will be organizations that ship product or run fleets of equipment.

The 50% cost share points the same way. Section 988 of the Energy Policy Act sets demonstration-project cost share at 50%. A $25 million federal request requires $25 million of non-federal match, and the federal share cannot exceed half of total project cost. A proposal below the minimum is ruled ineligible at compliance review, before any technical reviewer reads it.

Topic Area 1: refurbishment and reuse ($50M)

Who should lead: Electric utilities (investor-owned, municipal, and cooperative), joint action agencies, generation and transmission cooperatives, and refurbishment shops partnered with utilities.

What DOE wants: Programs that "reclaim, repair, refurbish, and recertify" grid equipment, including distribution and power transformers, circuit breakers, switchgear, reclosers, insulators, busbars, and high-voltage bushings, and return it to inventory. The NOFO suggests three approaches:

What DOE rejects: General waste management, household recycling technology, or anything that doesn't put "grid components back into a utility's stock or materials and subcomponents into grid supply chains."

How it's scored: Topic Area 1 merit criteria focus on readiness ("feasible and ready to implement, complete with material flows"), integration into the utility's normal workflows by the end of the award, and equipment that meets industry certification standards. Significance and Impact, the largest criterion at 40%, asks whether the program cuts procurement cost and procurement time.

Strategic read: At $2.5 million to $15 million over 24 months, Topic Area 1 suits a mid-size utility or a regional consortium. A storm-prone cooperative that currently scraps failed pole-top transformers is close to the ideal applicant. It has a steady supply of damaged units, a measurable baseline (units scrapped per year, average replacement lead time, cost per new unit), and a clear before-and-after story. DOE requires quantitative targets for lead-time reduction and "component re-entry rate," so start pulling those baseline figures from your asset management system now.

A consortium of smaller utilities with one shared refurbishment partner can reach the $2.5 million floor and the volume needed to show scalability. The geographic distribution policy factor may also favor a multi-state rural consortium over another large investor-owned utility.

Topic Area 2: alternative materials and subcomponents ($187M)

Most of the money is in Topic Area 2, and the requirements are much heavier.

Who should lead: U.S. grid equipment manufacturers, subcomponent makers (bushings, windings, cores, insulation), electrical steel and conductor producers, and battery energy storage system suppliers. Battery storage is explicitly in scope, which widens the field more than the transformer framing suggests.

The three-node rule. To pass the Phase 1 Go/No-Go, the team must include at least:

  1. Upstream materials or subcomponent suppliers
  2. A domestic manufacturer of the material or subcomponent
  3. First customers that integrate the component

The letter that disqualifies. Topic Area 2 applications without a signed Letter of Commitment from an upstream supply chain contributor (a feedstock supplier or manufacturing equipment supplier) are "non-compliant" and "will not receive a merit review evaluation." The letter is limited to one page and must state the contributor's role, the value of its contribution, any cost share, and why its participation is needed. This is the most likely reason a strong Topic Area 2 application could fail before review, and the commitment needs to be negotiated before November 20, not in January.

The Go/No-Go gate. Phase 1 (about 12 months) has to produce a set of planning deliverables: signed MOUs or teaming agreements; an aligned technical specification and manufacturability package covering process flow, equipment, QC, throughput, and yield; a component-level domestic content plan; evidence of first customers such as letters of intent, draft offtake terms, or purchase commitments; a facility, workforce, and commissioning plan; a cost model compared with imported incumbents; and a risk register. Only projects that pass move on to the 36-month Phase 2 manufacturing ramp under the same award. Projects that don't pass end after Phase 1.

In practice, DOE is funding Phase 1 to confirm that a supply chain exists on paper before paying for production. Applicants who already have draft offtake terms and supplier MOUs can present Phase 1 as a short confirmation step, and that reads as low risk to reviewers.

Strategic read: The $1 million floor is low enough for a specialized subcomponent maker. A domestic ceramic bushing producer, for example, could partner with a transformer OEM as first customer and a high-purity alumina supplier as upstream contributor. The $25 million ceiling is meant for steel and conductor-scale projects. Because the NOFO lists "the applicant's proportional contribution toward Topic Area 2's collective domestic capacity objective" as a merit factor, DOE will compare projects by how much domestic capacity each one adds per federal dollar. Put a number on capacity added (tons per year, units per year, percent of national demand) and present it clearly.

How the review works

Concept papers are scored on a single criterion, "Overall NOFO Responsiveness and Viability," with four equally weighted sub-factors: clear project description and advance over the state of the art; identified risks and the impact of DOE funding; team qualifications; and fit to NOFO objectives. DOE then encourages or discourages a full application. Under the standard DOE process described in NOFO Part 2, discouraged applicants may still submit, but few do well.

Full applications are scored on four weighted criteria:

CriterionWeight
Project Merit30%
Significance and Impact40%
Project Execution and Management15%
Team and Resources15%

Significance and Impact carries the most weight. The Topic Area 2 version asks whether the project "materially" expands U.S. capacity, increases domestic content, shortens lead times, gets equipment to first customers, creates jobs and supplier activity, and shows "demand certainty, private sector leverage, cost reduction potential." All of these are commercial measures, so write the application as an investment case.

The program policy factors include "advances the President's policy priorities," procurement of U.S. iron, steel, and manufactured products, geographic distribution, and "broad public support from the communities most directly impacted." Build America, Buy America applies to infrastructure components of awards, along with Davis-Bacon.

Eligibility details that catch applicants

A three-week plan to November 20

Week of November 2: Register on DOE eXCHANGE and confirm SAM.gov, UEI, and Login.gov access, since eXCHANGE submission depends on all three. Join the SCALED Teaming Partner List on eXCHANGE. Topic Area 2 applicants should look there for an upstream supplier or first customer, and partners will be looking for you. Choose a topic area and draft a one-paragraph project thesis with a quantified outcome.

Week of November 9: Get the upstream supplier and first-customer commitments in principle, even if only by email. Pull baseline figures: current lead times, import share of the target input, units scrapped per year. Confirm the source of 50% cost share and have your CFO sign off.

Week of November 16: Write the five-page project description to the four concept paper sub-factors. Use the one-page addendum to show the team has worked together before and has the facilities, which is a sub-factor in its own right. Submit by Thursday, November 19. Do not wait for 5:00 p.m. Friday.

December through February 8: If encouraged, build the full application around the Go/No-Go table (Topic Area 2) or the re-entry and lead-time metrics (Topic Area 1). Get the signed upstream Letter of Commitment early, as it is a pass/fail item.

The bottom line

SCALED is a manufacturing and procurement program set up as a federal grant. DOE wants refurbished transformers back in utility yards by 2029 and domestic substitutes on production lines by 2031. It will pay up to half the cost for teams that can show both with numbers. Teams that already have a supply chain and need a federal partner to scale it are well placed. Teams that are still forming the idea will have a hard time doing it in three weeks.

If you have the team and need help turning it into a seven-page concept paper before November 20, Granted can help you draft it.

Get AI Grants Delivered Weekly

New funding opportunities, deadline alerts, and grant writing tips every Tuesday.

Browse all NSF grants

More NSF Articles

Rural Texas Strong's $87 Million, 129-Provider Round: How Texas Is Spending Its $281 Million Rural Health Transformation Year and What Year Two Will Reward

On October 29, 2026, Texas announced $87.2 million in Rural Texas Strong grants to 129 rural health providers, its largest round yet from the $281.3 million first-year CMS Rural Health Transformation Program award. With weekly intent-to-award notices, roughly $224 million now announced across four rounds, and $1.4 billion expected over five years, here is what the awards reveal and how rural hospitals, clinics, EMS agencies and pharmacies should prepare for the next cycle.

Read article

DURIP FY2027 Carries $28 Million and Closes November 6 — Six Million Less Than Last Year, Ten Days Before NSF MRI

The FY2027 Defense University Research Instrumentation Program closes November 6, 2026 at 5:00 PM ET with roughly $28 million, awards from $50,000 to $3 million, and no cost-share requirement. It is down about $6 million from FY2026, it funds equipment and nothing else, and it lands ten days before the NSF MRI deadline. Here is how to split an equipment wishlist across two overlapping windows.

Read article

NSF Just Gave $30 Million to a Nonprofit That Screens Second Graders. The Match Requirement Is the Part Worth Copying.

On October 8, 2026 NSF's Technology, Innovation and Partnerships directorate awarded $30 million over four years to National Math Stars — fully matched by private philanthropy. A K-12 talent-identification nonprofit held the prime slot, not a university. That combination is the template, and NextGen Workforce is next.

Read article

Not sure which grants to apply for?

Use our free grant finder to search active federal funding opportunities by agency, eligibility, and deadline.

Find Grants

Ready to write your next grant?

Draft your proposal with Granted AI. Professional members win a grant in 12 months or get a full refund.

Backed by the Granted Guarantee